Skip to content
Free tool · For contractors

Are you overbilled or underbilled?

Your billing and your progress on a job rarely match. Enter four numbers from one job and see whether you're ahead on cash you haven't earned yet, or behind on money you've already earned.

1The job
2Where it stands today

Rough numbers are fine. Nothing you enter is saved or sent anywhere. It all stays in your browser.

How it works

Your progress sets what you've earned. Not your invoices.

This uses the cost-to-cost method most contractors and sureties rely on. Percent complete is your costs to date divided by your estimated total cost. Earned revenue is that percent times your contract. The gap between what you've earned and what you've billed is your over or under billing.

One job tells part of the story. Your WIP schedule puts every job side by side, and it's what your bank and surety read first.

Know Your Zero · Issue 06

Your WIP Schedule Says One Thing. Your Surety Wants to Hear Another.

What your surety is really reading in your WIP schedule, and how to get ahead of the questions.

Read the issue →